Cherryfield Project Update – October 23, 2026

October 23, 2026

By Ellie Mason, Habitat Restoration Project Manager

Since construction began in June, the Cherryfield Fish Passage Improvement Project has undergone a remarkable transformation.

What began with the removal of the decades-old dam structure and extensive work within the Narraguagus River has evolved into a new, nature-like fishway designed to improve passage for Atlantic salmon and other sea-run fish while maintaining the headpond and helping protect downtown Cherryfield from ice-related flooding. With the dam breached in late July, the step pools now in place, and water flowing freely through the newly constructed channel, the project has reached a major milestone in restoring connectivity along this important river.

As construction winds down for the season ahead of a planned return in the spring, attention has shifted from the river to improvements at Cable Pool Park, where a revitalized public gathering space is taking shape. Sargent Corporation has started constructing a new riverside amphitheater using granite blocks reclaimed during construction, established new walking paths, and begun restoring other areas altered by the project. The first round of vegetation planting is complete, with benches, picnic tables, additional landscaping, and a nature-based play space for children expected to take shape in the coming weeks.

While much has changed since June, we’re especially looking forward to watching how the river responds to the changing seasons. As fall rains arrive and winter approaches, water levels will naturally fluctuate in the fishway, bringing water into areas of the fishway that may currently appear dry. These seasonal changes are an important part of how the nature-like fishway is designed to function.

Although construction will pause for the winter, Cable Pool Park is expected to reopen to the community in early winter, allowing residents and visitors to enjoy the newly improved public space. Additional restoration, landscaping, and finishing work will resume in the spring as the project moves toward anticipated completion in spring 2028. What has taken shape over the past several months represents not only an important investment in the future of sea-run fish, but also a renewed connection between the Narraguagus River and the Cherryfield community.

None of this progress would have been possible without the patience, encouragement, and support of Cherryfield residents throughout this remarkable season of construction.

We recognize that a project of this scale has brought changes and challenges to daily life, and we are incredibly grateful for the patience, understanding, and enthusiasm Cherryfield residents have shown throughout the process.

Aside from the fantastic Cherryfield community, DSF also wishes to extend our appreciation to our partners in this project:

  • Maine Coast Heritage Trust
  • The Nature Conservancy in Maine
  • Atlantic Salmon Federation
  • Inter-Fluve
  • Sargent Corporation
  • Maine Department of Marine Resources

As we look ahead, we are excited to see this revitalized stretch of the Narraguagus River become a lasting resource for sea-run fish and a place for residents and visitors to enjoy for generations to come.